Price mismatch may impede India’s battery storage projects: report

  • India
  • May 19, 2026
  • 0 Comments
[anap_hero_image fallback=”https://th-i.thgim.com/public/news/national/zf31kp/article70999537.ece/alternates/LANDSCAPE_1200/iStock-1620576275.jpg”]

The Hindu

Price mismatch may impede India’s battery storage projects: report

Price mismatch may impede India’s battery storage projects: report Tariffs discovered in 2025 auctions increasingly don’t appear to be economically viable, says the report Published – May 19, 2026 10:50 pm IST – NEW DELHIJacob Koshy India’s clean…

India
May 19, 2026

[anap_share_buttons]

Price mismatch may impede India’s battery storage projects: report

Tariffs discovered in 2025 auctions increasingly don’t appear to be economically viable, says the report

Published – May 19, 2026 10:50 pm IST – NEW DELHI

Jacob KoshyJacob KoshyIndia’s clean energy transition is becoming increasingly dependent on energy storage systems as renewable power generation expands. Image for representation only.

India’s clean energy transition is becoming increasingly dependent on energy storage systems as renewable power generation expands. Image for representation only.
| Photo Credit: Getty Images/iStockphoto

India’s rapid expansion of battery energy storage procurement may be hard to execute as tariffs discovered in 2025 auctions increasingly don’t appear to be economically viable, according to a report released by the Institute for Energy Economics and Financial Analysis (IEEFA) and JMK Research & Analytics.

India’s clean energy transition is becoming increasingly dependent on energy storage systems as renewable power generation expands. Standalone energy storage tenders — where storage capacity is contracted independently of renewable generation assets — accounted for more than 71% of the country’s total energy storage tendered capacity in 2025, with standalone Battery Energy Storage System (BESS) projects comprising around 60% of this share.

During 2025, around 10.4 gigawatts (GW) of standalone BESS capacity was allocated across 18 tenders. The bulk of awarded capacity involved two-hour duration systems, particularly those designed to discharge twice daily to help meet morning and evening electricity demand peaks.

The report, Viability of Standalone Battery Energy Storage Tariffs Discovered in 2025, examines 18 auctions in which about 10.8 GW of standalone BESS capacity was tendered and roughly 10.4 GW allocated. It flags a widening disconnect between tariffs and underlying costs. “Between 2022 and 2025, tariff reduction far exceeded battery cost reductions. Average standalone BESS tariffs declined by 79.6% during this period, whereas battery pack prices fell by 36.5%,” it notes. Lithium carbonate prices in China — a key input for lithium iron phosphate cells — almost doubled between mid-2025 and December 2025, and China’s phased withdrawal of battery export rebates from April 2026 is expected to push landed battery costs in India higher. Tariff reduction “accelerated sharply in the second half of 2025,” the report observes, “suggesting speculative bidding behaviour.”

Then there is also the question of the antecedents of the project developers. Only 46.3% of allocated capacity went to firms, the authors classify, as having prior experience in the BESS sector. Of the top 15 awardees, 10 were new entrants, “including firms primarily engaged in unrelated industries such as food processing, mining and packaging.” 

‘Risky segment’

Based on benchmark estimates developed by JMK Research, a two-hour, two-cycle BESS system with a 12-year tenure would require tariffs of around ₹2.3 lakh/MW/month to remain financially viable under prevailing assumptions related to capital expenditure, operating costs and financing. Against this benchmark, nearly 75% of the allocated two-hour BESS capacity in 2025 falls into what the report categorises as a “risky” segment, where tariffs may be insufficient to support project execution.

India’s installed BESS capacity stood at around 1.8 GWh as of March 2026 — set against 50 GWh commissioned in the United States in 2025 and 65 GWh added by China in December 2025 alone. The report warns that cumulative commissioning delays of nine to 18 months could constrain renewable integration and India’s 500 GW renewable capacity target for 2030, and recommends cost-reflective tariff floors, stricter eligibility norms and a standardised payment security mechanism for storage.

Published – May 19, 2026 10:50 pm IST

Source & Attribution

This article was generated from an imported news source and rewritten for clarity and readability. View original source

[anap_related_posts]

  • Related Posts

    What did the Supreme Court say about bail under UAPA?

    What are the disagreements between recent Supreme Court rulings on UAPA bail? Why is bail so difficult under Section 43D(5) of the UAPA? What did the Court say in K.A.…

    Manipur CM assures NIA probe into abduction of Naga men

    Kuki Inpi Manipur extends shutdown since May 13 by another 48 hours to secure release of 14 Kuki people

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    You Missed

    Counting of votes in Bengal’s Falta Assembly repoll begins

    Manipur CM assures NIA probe into abduction of Naga men

    What did the Supreme Court say about bail under UAPA?

    A nation that makes its own weapons writes its destiny: Rajnath Singh

    Supreme Court registers suo motu case over death of Twisha Sharma

    News in Frames | The drying naulas of Uttarakhand